On October 27, 2026, Prensa Libre reported that thirteen companies requested authorization to take part in the mandatory technical visit to the Xan oil field in San Andrés, Petén. The visit, scheduled for October 26–30, is part of the tender led by Guatemala's Ministry of Energy and Mines (MEM) to close and dismantle the field. Logística Dos Mares is on that list.
For us, being there is not a formality. For four decades Xan was the country's most important oil field, and the way it is closed will say a lot about Guatemala's ability to carry out complex technical projects transparently and with respect for one of its most valuable ecosystems.
What is being tendered
According to the MEM's General Directorate of Hydrocarbons (DGH), the project includes:
- The closure of 59 oil wells and the dismantling of the field's other assets.
- An estimated budget of Q375 million (about US$49 million), funded by the State.
- A three-year execution period.
The technical visit is a requirement of the tender rules published on Guatecompras: without it, no company can submit a bid. Over five days, company representatives inspect the storage tanks, flow lines, power generation facilities, workshops and the surface condition of the wells. Because access is difficult, each inspection day lasts 10 to 14 hours, and every company covers its own transport, lodging and meals.
The end of an era
Oil contract 2-85, under which Perenco operated the field for 40 years, expired on August 12, 2025, and the State took the field back. Since then, the challenge is no longer to produce, but to close it properly.
The field lies next to Laguna del Tigre National Park, inside the Maya Biosphere Reserve. That is why its closure is much more than an engineering job: Guatemala's National Council of Protected Areas (Conap) is carrying out a ten-year ecological restoration plan for the area. A poorly sealed well or a badly removed facility can affect soil and aquifers for decades.
Why Logística Dos Mares is part of this process
Since 2007, Logística Dos Mares has worked in civil works, road infrastructure, machinery leasing and energy project development. We also lead a consortium of companies with complementary capabilities in energy project development and operation.
A closure like Xan's requires exactly that combination: moving heavy machinery into a hard-to-reach area, carrying out civil works in the field, removing industrial facilities and leaving the land ready for recovery. That is why we believe going to the site is the only serious way to size up a project of this scale.
What a responsible closure requires
In our view, a project like this must meet four conditions:
- Technical safety: every well must be sealed permanently and verifiably.
- Environmental management: tanks, flow lines and facilities must be dismantled without creating new liabilities in a protected area.
- Transparency: the process must stay on Guatecompras, with clear rules and open competition. Thirteen companies asking to join the visit is a good sign.
- Long-term vision: the closure must leave the area ready for Conap's restoration plan.
Next steps
According to Guatemala's official news agency (AGN), bids are due on November 23, 2026, at the MEM (NOG 30311551). At Logística Dos Mares we will follow the process closely, convinced that Guatemala's development is also measured by how it closes the chapters it ends.